PROJECT TRACKER

Every announced reconstruction project, and how far it actually got

The gap between announcement and asphalt is the most under-covered story in Syria. This table tracks each project from the press release to the ground, and says plainly which stage the evidence supports.


  • $13bn announced across tracked projects
  • 13 projects tracked
  • 4 with work or operations under way
  • 0 disbursement figures published

Not one funder publishes what it has actually spent. That is the number this tracker exists to force into the open.

Why doesn't this total match the $25.9bn in signed MoUs?

This tracker totals less than the USD 25.9 billion in signed MoUs we cite elsewhere on the site, and the difference is not an error. That 25.9 figure is Karam Shaar Advisory's aggregate across 40 agreements; for most of those 40, no public source names the project, the site or the counterparty in enough detail to make a row. We track named projects only. The gap between this total and 25.9 is therefore a measure of how much announced Syrian investment is still, in public, just a number — which is itself one of the findings.

Where the money is in the pipeline

  1. 4 Announced
  2. 4 Signed
  3. 1 Financed
  4. 4 Under way
  5. 0 Complete

Status is the furthest stage we can evidence from a named source — not the furthest stage claimed.

Announced value by sector

Announced value by sector

USD, nominal. Announced commitments, not money spent. Sectors whose projects carry no disclosed value appear at zero.

Energy alone accounts for 55% of tracked announced value, while housing — the largest line in the reconstruction bill — carries no disclosed value at all.

Source: Umran Project Tracker (2026-07-27) Estimate

View data
Sector Announced Project
Energy $7.1bn 3
Aviation $2.0bn 2
Transport $2.0bn 1
Ports & logistics $1.1bn 2
Telecoms $800m 1
Education $30m 2
Housing $0 1
Reconstruction services $0 1

Where the projects are

Count of tracked projects by governorate.

  • Not allocated 6
  • Damascus 2
  • Aleppo 1
  • Tartous 1
  • Lattakia 1
  • Rif Dimashq 1
  • Multiple 1

Projects marked not allocated are national in scope, or their source names no location.

The tracker

Showing 13 of 13 projects · $13bn announced

Every announced reconstruction project, and how far it actually got
Source
Energy Not allocated UCC Holding-led consortium (Power International Holding) Qatar / Türkiye / USA $7.0bn Signed reuters.com Sourced
Aviation Aleppo Saudi investment fund in Syria Saudi Arabia $2.0bn Announced english.alarabiya.net Reported
Transport Damascus Al-Wataniya UAE $2.0bn Announced karamshaar.com Reported
Ports & logistics Tartous DP World UAE $800m Under way dpworld.com Sourced
Telecoms Not allocated stc (Saudi Telecom Company) Saudi Arabia $800m Announced aljazeera.com Reported
Ports & logistics Lattakia CMA CGM France $260m Under way bairdmaritime.com Sourced
Energy Not allocated World Bank (IDA grant) Multilateral $146m Financed worldbank.org Sourced
Education Not allocated Azerbaijan, implemented by ISESCO Azerbaijan $30m Signed english.enabbaladi.net Reported
Aviation Not allocated flynas with the Syrian Civil Aviation Authority Saudi Arabia / Syria Signed aljazeera.com Reported
Energy Not allocated ACWA Power Saudi Arabia Announced acwapower.com Reported
Housing Rif Dimashq Abyat with the General Housing Authority Saudi Arabia / Syria Signed sana.sy Reported
Education Multiple Germany (KfW/BMZ), Japan, Canada, Finland, Norway, Bulgaria, AECID Multilateral Under way unicef.org Sourced
Reconstruction services Damascus King Salman Humanitarian Aid and Relief Centre Saudi Arabia Under way newarab.com Reported

How a row gets its status

One row per announced reconstruction project. Status is the furthest stage we can evidence from a named source, never the furthest stage claimed by a party to the deal. 'announced' = publicly stated, no signed instrument we could find. 'signed' = an MoU or concession has been signed. 'financed' = financial close or a disbursed grant. 'underway' = physical work or operations have begun. 'complete' = delivered. Where a party says 'under construction' and no independent report confirms it, we hold the row at its last evidenced stage and say so in the note.

On the money column

Announced value is the headline figure as disclosed, in nominal US dollars. It is what was announced, not what has been spent. No public source reports disbursement against these commitments — closing that gap is the reason this tracker exists.

What this tracker cannot tell you

  • Disbursement is not published for any project on this list. Announced value is therefore an upper bound on activity, not a measure of it.
  • Several 2026 packages were announced as portfolio totals — Saudi Arabia's $6.4bn forum package, the $14bn twelve-project August announcement — without a public project-by-project split. We track the components we can name and leave the remainder off the tracker rather than inventing a breakdown.
  • Governorate is left null where the source does not state one. Roughly a third of announced value is national or unallocated.
  • Completion dates are as stated by the developer. None has been independently verified.

Spotted a project we're missing, or a status that's wrong?

Send us the source